GE Repair update as of April 01, 2016

Scheduled Activities:


• The contractor will continue removing of the identified concrete and reinforcement of the parking
garage west side, Level 4.
• The contractor will install new reinforcement and concrete to the prepared areas on Level 4
• Level 3 wash areas will be tested and locations that require repairs will be identified
• The contractor is removing the old joint sealant from all plank joint connections on Level 4 west
• The contractor will inspect the plank joint connections and make any repairs necessary
• The contractor may perform some joint repair and re-striping of the Level 5, Roof areas as weather
and parking coordination permits

Garage East Repairs as of April 01, 2016 PDF Icon