Garage East Repair Update 04-11-2016

Scheduled Activities:


• The contractor continues with the repairs weather permitting:
• There will be no access to the elevators or the northwest stair tower (#2) from levels 3 or 4
• The contractor will continue testing on level 3 and identifying areas for repair
• Continue with the demolition of the identified areas on Level 4
• Contractor will continue installation of the new reinforcement into the repair sections
• Level 4 will require power washing in the repair areas
• Concrete will be installed (weather permitting) into the prepared areas
• Contractor continues to remove the sealant from the plank joints to inspect and repair connection areas

Garage East Repairs as of April 11, 2016