Kennedy Square Development Timeline
| Date | Completed | Milestone |
| 2008 | √ √ √ √ √ √ |
ESDC announces transfer of property to Upstate Phase I Environmental Review Completed Phase II Enviromental Review Completed Asbestos Survey Started Public Comment Hearing CNY Biotech Research Center Design Begins |
| Winter 2009 | √ √ √ √ √ √ √ |
SUNY Upstate Takes Title to the Property SEQR Process Begins State Historic Preservation Act Process Begins Property Boundary Survey Completed Asbestos Survey Completed Existing Underground Storage Tanks Removed Demolition Design Documents Developed |
| April 2009 | √ | SEQR Process Completed |
| April 2009 | √ | State Historic Preservation Act Process Ends |
| June 2009 | CNY Biotech Research Center Design Completed | |
| June 2009 | Development RFP is Completed | |
| July 14, 2009 | Site Demolition Begins | |
| September 2009 | Site Demolition Completed | |
| September 2009 | CNY BRC Construction Starts | |
| October 2009 | Select a Developer for the Site | |
| July 2010 | Phase I of Development Begins | |
| December 2010 | CNY BRC Constuction Completed | |
| December 2010 | Development is completed |