Kennedy Square Development Timeline

Date Completed Milestone
2008




ESDC announces transfer of property to Upstate
Phase I Environmental Review Completed
Phase II Enviromental Review Completed
Asbestos Survey Started
Public Comment Hearing
CNY Biotech Research Center Design Begins
Winter 2009





SUNY Upstate Takes Title to the Property
SEQR Process Begins
State Historic Preservation Act Process Begins
Property Boundary Survey Completed
Asbestos Survey Completed
Existing Underground Storage Tanks Removed
Demolition Design Documents Developed
April 2009 SEQR Process Completed
April 2009 State Historic Preservation Act Process Ends
June 2009   CNY Biotech Research Center Design Completed
June 2009   Development RFP is Completed
July 14, 2009   Site Demolition Begins
September 2009   Site Demolition Completed
September 2009   CNY BRC Construction Starts
October 2009   Select a Developer for the Site
July 2010   Phase I of Development Begins
December 2010   CNY BRC Constuction Completed
December 2010   Development is completed